INA-Industrija nafte (INA) has successfully started up the new Delayed Coker Unit at the Rijeka Refinery, following mechanical completion and commissioning; operational control was transferred to INA and feedstock was introduced on September 1, 2026—marking a major milestone in the Rijeka Refinery Upgrade Project.
INA-Industrija nafte, d.d. (Zagreb, Croatia) has reached another major milestone at the Rijeka Refinery Upgrade Project. Following the successful achievement of mechanical completion and commissioning, the new Delayed Coker Unit (DCU) has successfully achieved start-up. Following the transfer of operational responsibility to INA, feedstock was introduced into the unit on September 1, 2026, marking the […]
The post INA’s Rijeka Refinery achieves successful start-up of delayed coker unit appeared first on Chemical Engineering.